Winter Update 2025
In this update you will see that we are again concentrating on the ongoing machining of the cylinder castings, but we are also mentioning other parts that have been worked on recently. We start with the pattern for the handbrake column casting and the actual casting being machined. This now only requires the fixing holes drilling and the mating face where it sits up to the sidetank being formed for it to be finished. What follows is the machining of the bore for the piston ro
Dec 22, 2025


Autumn Update 2025
John Dunn is progressing well with the machining of the cylinders. What follows is a series of images showing the remaining work on the...
Oct 10, 2025


Summer Update 2025
As mentioned in the last update, after being allowed to season in the workshop for almost a year, the cylinders were moved to John Dunn Engineering for machining to be carried out. Firstly, the castings needed to be set up on the borer table for them to be marked out, this can be seen in the accompanying illustrations. It has also been necessary to make suitable tooling and stops to make the machining operation easier. Also, because of the unusual shape of the castings, vario
Jul 1, 2025


Gowrie at CLT Seal LTD
The Hengist Locomotive Project hosted their annual open day on Saturday, April 13 2024, at CTL Seal LTD in Sheffield showing the two...
Apr 23, 2025


Spring Update 2025
At the moment Stuart is concentrating on getting the trailing bogie to a suitable condition to go to the Hengist open day at CTL Seal on...
Mar 28, 2025